Woodridge Village Excavation

News

Woodridge Village Excavation and Removal Contract Ends

(Note: Within an hour of posting this, I received additional information from a source familiar with Federal grants and have updated the section on Funding below.) Harris County Flood Control District (HCFCD) and Sprint Sand & Clay have ended their Woodridge Village excavation and removal (E&R) contract. As of Friday afternoon, 11/24/23, Sprint had removed […]

The post Woodridge Village Excavation and Removal Contract Ends appeared first on Reduce Flooding.

Read More
News

Woodridge Village Excavation Rate Increased Slightly in October

During the month of October 2023, Sprint Sand & Clay excavated another 5,754 cubic yards (CY) of dirt from a new stormwater detention basin on Harris County Flood Control District’s (HCFCD)Woodridge Village property. Compare that to 5,698 cubic yards in September. The new “total to date” is now 156,478 cubic yards. October’s 5,754 CY exceeds […]

The post Woodridge Village Excavation Rate Increased Slightly in October appeared first on Reduce Flooding.

Read More
News

Woodridge Village Excavation Activity Almost Doubles

Compared to July, Woodridge Village excavation activity almost doubled in August. As of close of business on September 6, 2023, Harris County Flood Control District (HCFCD) contractor Sprint Sand and Clay has excavated 146,104 cubic yards of material to expand the stormwater detention basin capacity on Woodridge Village. At the end of July, Sprint had […]

The post Woodridge Village Excavation Activity Almost Doubles appeared first on Reduce Flooding.

Read More
News

In May, Woodridge Village Excavation Total Reached Almost 124,000 Cubic Yards

Harris County Flood Control District’s (HCFCD) Woodridge Village Excavation and Removal contract for 500,000 cubic yards with Sprint Sand & Clay is almost one-quarter complete. Sprint excavated approximately another 9,000 cubic yards in May (5.8 acre feet). That’s almost double the monthly minimum and brings the total up to 123,882 cubic yards. Stormwater from Woodridge Village flooded […]

The post In May, Woodridge Village Excavation Total Reached Almost 124,000 Cubic Yards appeared first on Reduce Flooding.

Read More
News

Woodridge Village Excavation Approaching Atlas-14 Requirement

Harris County Flood Control District’s (HCFCD) Woodridge Village Excavation and Removal contract with Sprint Sand & Clay continues progressing nicely. The volume excavated last month shows a continued rebound in activity after a dip last year when the housing market slowed. As of the end of April, Sprint has completed approximately 23% of its 500,000-cubic-yard […]

The post Woodridge Village Excavation Approaching Atlas-14 Requirement appeared first on Reduce Flooding.

Read More
News

July Update: Woodridge Village Excavation Rate Slows Slightly

The pace of excavation and removal of up to 500,000 cubic yards of soil from Woodridge Village has slowed slightly in recent months. That may be due to rising interest rates, which have slowed housing starts. Contractors use excavated dirt to elevate homesites in new developments. But the Census Bureau says housing starts in June […]

The post July Update: Woodridge Village Excavation Rate Slows Slightly appeared first on Reduce Flooding.

Read More