UPRR - HoustonNewMedia.org https://houstonnewmedia.org/tag/uprr/ Building "Bridges" Across the Bayou City! Wed, 05 Nov 2025 21:59:41 +0000 en-US hourly 1 https://wordpress.org/?v=6.9 https://i0.wp.com/houstonnewmedia.org/wp-content/uploads/2022/11/cropped-cropped-Houston.png?fit=32%2C32&ssl=1 UPRR - HoustonNewMedia.org https://houstonnewmedia.org/tag/uprr/ 32 32 103504436 Northpark Update: Building Blocks Falling into Place https://houstonnewmedia.org/northpark-update-building-blocks-falling-into-place/?utm_source=rss&utm_medium=rss&utm_campaign=northpark-update-building-blocks-falling-into-place Wed, 05 Nov 2025 21:59:41 +0000 https://reduceflooding.com/?p=54391 11/5/25 – From ground level, a driver may not see all the progress being made on the first all-weather evacuation route from Kingwood. But from the air, it’s unmistakable. One can clearly see the pieces of the final Northpark project coming together. In the last week, contractors have: Below are pictures taken on Monday, 11/3/25 […]

The post Northpark Update: Building Blocks Falling into Place appeared first on Reduce Flooding.

The post Northpark Update: Building Blocks Falling into Place first appeared on HoustonNewMedia.org.

The post Northpark Update: Building Blocks Falling into Place appeared first on HoustonNewMedia.org.

]]>
1058945
Major Northpark Milestone: Bore Under Tracks Completed https://houstonnewmedia.org/major-northpark-milestone-bore-under-tracks-completed/?utm_source=rss&utm_medium=rss&utm_campaign=major-northpark-milestone-bore-under-tracks-completed Sat, 18 Oct 2025 16:23:12 +0000 https://reduceflooding.com/?p=54105 10/18/2025 – Yesterday, on 10/17/2025, the Northpark Expansion project reached a major milestone. Some might say the project cleared a major hurdle, except the hurdle is about 15 feet below the UnionPacific Railroad tracks. Whatever you call it, the completion of the second bore under the railroad tracks caused jubilation among board members of the […]

The post Major Northpark Milestone: Bore Under Tracks Completed appeared first on Reduce Flooding.

The post Major Northpark Milestone: Bore Under Tracks Completed first appeared on HoustonNewMedia.org.

The post Major Northpark Milestone: Bore Under Tracks Completed appeared first on HoustonNewMedia.org.

]]>
1047359
Northpark Contractors Start Boring Under Railroad Tracks https://houstonnewmedia.org/northpark-contractors-start-boring-under-railroad-tracks/?utm_source=rss&utm_medium=rss&utm_campaign=northpark-contractors-start-boring-under-railroad-tracks Sat, 17 May 2025 16:11:38 +0000 https://reduceflooding.com/?p=51111 5/17/25 – Contractors have finally started boring under UnionPacific Railroad (UPRR) tracks to connect Northpark drainage east and west of Loop 494. That crucial connection is a key to beginning many other parts of the Northpark expansion project. Lake Houston Redevelopment Authority first contacted UPRR about running Northpark drainage under their tracks ten years ago. […]

The post Northpark Contractors Start Boring Under Railroad Tracks appeared first on Reduce Flooding.

The post Northpark Contractors Start Boring Under Railroad Tracks first appeared on HoustonNewMedia.org.

The post Northpark Contractors Start Boring Under Railroad Tracks appeared first on HoustonNewMedia.org.

]]>
954351
How Wide Will Northpark Be When Done? https://houstonnewmedia.org/how-wide-will-northpark-be-when-done/?utm_source=rss&utm_medium=rss&utm_campaign=how-wide-will-northpark-be-when-done Thu, 13 Mar 2025 21:24:40 +0000 https://reduceflooding.com/?p=49731 3/13/25 – Just how wide will Northpark be when construction is complete? After the UnionPacific Railroad finished installing concrete road crossing panels last week we now have a visual cue. It’s going to be WIDE! With a capital W! Approximately three times wider than it currently is. See the pictures below taken this morning. Northpark […]

The post How Wide Will Northpark Be When Done? appeared first on Reduce Flooding.

The post How Wide Will Northpark Be When Done? first appeared on HoustonNewMedia.org.

The post How Wide Will Northpark Be When Done? appeared first on HoustonNewMedia.org.

]]>
918587
UPRR Almost Finished, Northpark to Reopen This Afternoon https://houstonnewmedia.org/uprr-almost-finished-northpark-to-reopen-this-afternoon/?utm_source=rss&utm_medium=rss&utm_campaign=uprr-almost-finished-northpark-to-reopen-this-afternoon Fri, 07 Mar 2025 17:49:24 +0000 https://reduceflooding.com/?p=49617 3/7/25 Updated at 2:30 PM– The UnionPacific Railroad (UPRR) has almost finished with Northpark work that caused a three day closure of one of two major traffic arteries out of Kingwood. UPRR hopes to reopen Northpark this afternoon. They say it should be open for evening rush hour. Reasons for Closure UPRR installed a single […]

The post UPRR Almost Finished, Northpark to Reopen This Afternoon appeared first on Reduce Flooding.

The post UPRR Almost Finished, Northpark to Reopen This Afternoon first appeared on HoustonNewMedia.org.

The post UPRR Almost Finished, Northpark to Reopen This Afternoon appeared first on HoustonNewMedia.org.

]]>
915333
UPRR Inserts New 200-Foot Section of Track Across Northpark https://houstonnewmedia.org/uprr-inserts-new-200-foot-section-of-track-across-northpark/?utm_source=rss&utm_medium=rss&utm_campaign=uprr-inserts-new-200-foot-section-of-track-across-northpark Thu, 06 Mar 2025 17:38:18 +0000 https://reduceflooding.com/?p=49597 3/6/25 – UnionPacific Railroad (UPRR) has finished splicing a 55,000-pound, 200-foot-long, single section of track into their line across Northpark Drive in Kingwood. However, more work still needs to be done. UPRR must still: Heavy Lifting Completed The hardest part of the job is now complete, though. The single-section splice will stabilize the track through […]

The post UPRR Inserts New 200-Foot Section of Track Across Northpark appeared first on Reduce Flooding.

The post UPRR Inserts New 200-Foot Section of Track Across Northpark first appeared on HoustonNewMedia.org.

The post UPRR Inserts New 200-Foot Section of Track Across Northpark appeared first on HoustonNewMedia.org.

]]>
914445
Northpark Closed 3 Days as UPRR Replaces Tracks, Signals https://houstonnewmedia.org/northpark-closed-3-days-as-uprr-replaces-tracks-signals/?utm_source=rss&utm_medium=rss&utm_campaign=northpark-closed-3-days-as-uprr-replaces-tracks-signals Wed, 05 Mar 2025 17:55:21 +0000 https://reduceflooding.com/?p=49579 3/5/25 – This morning, the UnionPacific Railroad (UPRR) closed Northpark Drive to replace a 200 foot section of track and install new signals. The replacement is necessary because the Lake Houston Redevelopment Authority/TIRZ 10 is expanding Northpark Drive to handle increased traffic and to create the first all-weather evacuation route from Kingwood. The expansion project […]

The post Northpark Closed 3 Days as UPRR Replaces Tracks, Signals appeared first on Reduce Flooding.

The post Northpark Closed 3 Days as UPRR Replaces Tracks, Signals first appeared on HoustonNewMedia.org.

The post Northpark Closed 3 Days as UPRR Replaces Tracks, Signals appeared first on HoustonNewMedia.org.

]]>
914223
Northpark Will Close at UPRR Tracks One Week from Today for Three Days https://houstonnewmedia.org/northpark-will-close-at-uprr-tracks-one-week-from-today-for-three-days/?utm_source=rss&utm_medium=rss&utm_campaign=northpark-will-close-at-uprr-tracks-one-week-from-today-for-three-days Thu, 27 Feb 2025 00:14:27 +0000 https://reduceflooding.com/?p=49424 2/26/25 – One week from today, Northpark Drive will close for three days. UnionPacific Railroad (UPRR) will maneuver a two-hundred-foot section of track and ties – welded and bolted into a single, massive unit – into place across what will become ten lanes of traffic and two sidewalks. Section Already Assembled, Ready, Waiting UPRR has […]

The post Northpark Will Close at UPRR Tracks One Week from Today for Three Days appeared first on Reduce Flooding.

The post Northpark Will Close at UPRR Tracks One Week from Today for Three Days first appeared on HoustonNewMedia.org.

The post Northpark Will Close at UPRR Tracks One Week from Today for Three Days appeared first on HoustonNewMedia.org.

]]>
909694
UPRR Getting Rails Ready for Northpark Closure https://houstonnewmedia.org/uprr-getting-rails-ready-for-northpark-closure/?utm_source=rss&utm_medium=rss&utm_campaign=uprr-getting-rails-ready-for-northpark-closure Fri, 21 Feb 2025 22:34:07 +0000 https://reduceflooding.com/?p=49361 2/21/25 – The UnionPacific Railroad (UPRR) has started preparing rails that it will place in one 200-foot long section across 10 lanes of Northpark Drive traffic. The closure of Northpark for the installation is still scheduled for March 5-7. UPRR is prepping the rails in the old northbound lanes of Loop 494 immediately north of […]

The post UPRR Getting Rails Ready for Northpark Closure appeared first on Reduce Flooding.

The post UPRR Getting Rails Ready for Northpark Closure first appeared on HoustonNewMedia.org.

The post UPRR Getting Rails Ready for Northpark Closure appeared first on HoustonNewMedia.org.

]]>
907295
More of Old Northpark Drive Disappears https://houstonnewmedia.org/more-of-old-northpark-drive-disappears/?utm_source=rss&utm_medium=rss&utm_campaign=more-of-old-northpark-drive-disappears Fri, 24 Jan 2025 00:33:48 +0000 https://reduceflooding.com/?p=48796 1/23/25 – In an effort to build the first all-weather evacuation route from Kingwood along Northpark Drive, contractors this week took a brief break – for the weather. But today, they were back at it. Here’s where things stand in the last full week of January. Demolition, Drainage and Weather Delay The Lake Houston Redevelopment […]

The post More of Old Northpark Drive Disappears appeared first on Reduce Flooding.

The post More of Old Northpark Drive Disappears first appeared on HoustonNewMedia.org.

The post More of Old Northpark Drive Disappears appeared first on HoustonNewMedia.org.

]]>
887384
Northpark Construction Sequence Changing https://houstonnewmedia.org/northpark-construction-sequence-changing/?utm_source=rss&utm_medium=rss&utm_campaign=northpark-construction-sequence-changing Mon, 19 Aug 2024 02:03:06 +0000 https://reduceflooding.com/?p=46516 8/18/24 – The sequence and timing of upcoming construction steps for the Northpark Drive Expansion Project is changing. Project Manager Ralph De Leon wants the public to know what will change, why and when between now and the end of the year. All parties involved in the construction met last week and agreed to the […]

The post Northpark Construction Sequence Changing appeared first on Reduce Flooding.

The post Northpark Construction Sequence Changing first appeared on HoustonNewMedia.org.

The post Northpark Construction Sequence Changing appeared first on HoustonNewMedia.org.

]]>