Taylor Gully Preliminary Engineering Study

News

New Woodridge Village Detention Basin About 12% Excavated, Engineering Study Almost Done

A new Woodridge Village Stormwater Detention Basin that could almost double detention capacity on the site continues to move forward slowly as housing starts slow. The trend at Woodridge seems consistent with other excavation and removal (E&R) contracts countywide. Meanwhile, the first draft of a preliminary engineering study for the Woodridge site and Taylor Gully […]

The post New Woodridge Village Detention Basin About 12% Excavated, Engineering Study Almost Done appeared first on Reduce Flooding.

Read More
News

Kingwood Diversion Ditch and Taylor Gully Preliminary Engineering Projects Begin

On June 29, 2021, Harris County Commissioners approved two contracts for preliminary engineering on the Kingwood Diversion Ditch and Taylor Gully Projects. This week, I’ve been getting reports of boots on the ground. So I grabbed my camera and went looking for activity this morning. I found a soil survey truck at Kingwood Drive next […]

The post Kingwood Diversion Ditch and Taylor Gully Preliminary Engineering Projects Begin appeared first on Reduce Flooding.

Read More
News

Commissioners Approve Excavation Contract for Regional Detention Pond on Taylor Gully

In yesterday’s Harris County Commissioners Court meeting, commissioners unanimously approved a contract with Spring Sand & Clay LLC for excavation of a regional detention pond on Taylor Gully in Montgomery County at the Woodridge Village site. Preliminary Engineering Began in Early July Earlier this year, Harris County purchased Woodridge Village from Perry Homes for this […]

The post Commissioners Approve Excavation Contract for Regional Detention Pond on Taylor Gully appeared first on Reduce Flooding.

Read More
News

HCFCD Taylor Gully Repair Project Approximately One-Third Complete

On January 19, I posted about Harris County Flood Control District’s (HCFCD) second major repair project on Taylor Gully since 2019. Thirty-nine days later, HCFCD has completed about one third of the project. They have now started on the downstream side of the Maple Bend Bridge in Kingwood’s Woodstream Village. Pictures of Work to Date […]

The post HCFCD Taylor Gully Repair Project Approximately One-Third Complete appeared first on Reduce Flooding.

Read More