Progress Report: Woodridge Village Excavation and Removal Contract
As of the end of June 2022, Harris County Flood Control District (HCFCD) had removed 42,483 cubic yards of dirt from the Woodridge Village property in Montgomery County. The dirt is part of an excavation and removal (E&R) contract that allows removal of up to 500,000 cubic yards. That amount would double the floodwater detention […]