Woodridge Village Plans Still on Hold, But that Could Change Soon

Back in November 2023, Harris County Flood Control District (HCFCD) terminated its excavation and removal contract with Sprint Sand and Clay. The 2021 contract called for Sprint to remove up to 500,000 cubic yards of material from Woodridge Village. Had the full amount been excavated, it would have more than doubled the stormwater detention basin […]

The post Woodridge Village Plans Still on Hold, But that Could Change Soon appeared first on Reduce Flooding.

Read More
News

Woodridge Village Excavation Reached 92% of Atlas-14 Requirements in June

At the end of June, stormwater detention basin excavation on Harris County Flood Control District’s (HCFCD) Woodridge Village property reached 92% of Atlas-14 requirements. When HCFCD bought the property from Perry Homes in 2021, it had only 70% of the required detention capacity under Atlas 14. Atlas-14 defines the current standard for safely containing a […]

The post Woodridge Village Excavation Reached 92% of Atlas-14 Requirements in June appeared first on Reduce Flooding.

Read More
News

In May, Woodridge Village Excavation Total Reached Almost 124,000 Cubic Yards

Harris County Flood Control District’s (HCFCD) Woodridge Village Excavation and Removal contract for 500,000 cubic yards with Sprint Sand & Clay is almost one-quarter complete. Sprint excavated approximately another 9,000 cubic yards in May (5.8 acre feet). That’s almost double the monthly minimum and brings the total up to 123,882 cubic yards. Stormwater from Woodridge Village flooded […]

The post In May, Woodridge Village Excavation Total Reached Almost 124,000 Cubic Yards appeared first on Reduce Flooding.

Read More
News

Rate of Woodridge Village Excavation Increases 47%

The rate of excavation for another stormwater detention basin on the Woodridge Village property picked up 47% in the last five weeks. That’s compared to the weekly average since Sprint Sand and Clay began excavating last year under the terms of its Excavation and Removal (E&R) contract with Harris County Flood Control District (HCFCD). Demand […]

The post Rate of Woodridge Village Excavation Increases 47% appeared first on Reduce Flooding.

Read More
News

Progress Report New Woodridge Village Floodwater Detention Basin

A new floodwater detention basin that will ultimately more than double the capacity of Woodridge Village is expanding slowly but steadily. To date, 33,159 cubic yards have been excavated! The pictures below show progress since the start of work in late January. Photos showing Progress Harris County Flood Control District (HCFCD) announced the project on 11/24/2021. […]

The post Progress Report New Woodridge Village Floodwater Detention Basin appeared first on Reduce Flooding.

Read More
News

Excavation of Additional Woodridge Village Detention Pond to Begin Soon

Here’s something to give thanks for on Thanksgiving. Harris County Flood Control District (HCFCD) announced Wednesday, 11/24/21, that Sprint Sand & Clay could begin excavation of another large detention pond on the Woodridge Village property as early as November 29. Lack of detention pond capacity on the property while it was being cleared contributed to […]

The post Excavation of Additional Woodridge Village Detention Pond to Begin Soon appeared first on Reduce Flooding.

Read More